AltaLink Windrise Windy Flats Substation Upgrade
High-voltage substation upgrade including a 400 MVA autotransformer, protection system modernization, and full SCADA integration in Fort Macleod, AB.
Submit your request online and our team will quickly assess the situation and coordinate the right support for your site. Or call us directly for immediate assistance.
The form could not be loaded. Please try again later.
Executed startup commissioning for a new mission-critical data center, covering switchgear, UPS, PDUs, protection relay testing, SCADA/BMS integration, and full IST.

From challenge to
Before a new data center can carry live load, every part of its power system has to be proven. Spark Power led startup commissioning for a new mission-critical facility, testing and verifying the electrical systems from end to end so the site was ready for live operations.
How we
The metrics